Site Information |
Site ID |
ROM206 |
Site name |
Rocky Mtn NP Collocated |
County |
Larimer |
State abbreviation |
CO |
AQS ID |
080690007 |
Latitude; decimal degrees |
40.278129 |
Longitude; decimal degrees |
-105.545635 |
Elevation; m |
2742 |
Operating agency |
EPA |
Start date |
06/26/2001 |
Primary Land Use |
Forest |
Terrain surrounding site |
Complex |
NADP/NTN site ID |
CO19 |
Distance to nearest NTN site; km |
9.987 |
Co-located NADP/AMoN Site ID |
CO88 |
View Map |
View Map |
|
Graphical Results |
Composition of total nitrogen deposition by species |
 |
Trends in total nitrogen deposition |
 |
Trends in wet and dry nitrogen deposition |
 |
Composition of total sulfur deposition by species |
 |
Trends in total sulfur deposition |
 |
Trends in wet and dry sulfur deposition |
 |
Trend in maximum 8-hour average ozone concentrations |
 |
Trend in 3-year average of ozone W126 index |
 |
|
|
Site History |
SHELTER_TEMPERATURE : A/C and Heat logger control installed. |
05-NOV-15 |
NOYDIF : Dryer installed in NO/NOy bypass box. |
18-MAY-15 |
OZONE : Air compressor with silica gel and charcoal canisters installed for ozone zero air |
14-APR-15 |
OZONE : Knock-out bottle removed. |
21-MAY-14 |
OZONE : New certification range for site transfer standard |
21-MAY-14 |
OZONE : Foam insulation added to sample line. |
21-MAY-14 |
OZONE : ZSP order changed to SPZ. |
25-OCT-13 |
OZONE : Knockout bottle reinstalled in ozone sample line. |
30-NOV-12 |
OZONE : Knockout bottle taken out of ozone sample line. |
07-MAY-12 |
OZONE : Replacement pressure transducer installed in site analyzer. |
07-MAY-12 |
OZONE : 10 ft. exhaust tubing added to both analyzers. |
07-MAY-12 |
TEMPERATURE : 9m temperature measurement with passive aspiration installed. |
07-NOV-11 |
SIGMA_THETA : Sensor unwired. |
07-NOV-11 |
WINDSPEED_SCALAR : Sensor unwired. |
07-NOV-11 |
WIND_DIRECTION : Sensor unwired. |
07-NOV-11 |
WINDSPEED : Sensor unwired. |
07-NOV-11 |
TEMP2 : Sensor unwired. |
07-NOV-11 |
RELATIVE_HUMIDITY : Sensor unwired. |
07-NOV-11 |
OZONE : 40CFR Part 58 ozone site upgrade completed using Level 2 site transfer standard. |
04-MAY-11 |
OZONE : Ozone sample line filter removed from inside the shelter. |
03-MAY-11 |
OZONE : Ozone tubing changed from 3/8 inch to 1/4 inch. |
06-NOV-10 |
OZONE : 40CFR Part 58 ozone site installed using independent site transfer standard. |
06-JUL-10 |
OZONE : Prototype 40CFR Part 58 ozone site installed using ozone generator as site transfer standard. |
11-NOV-09 |
DATALOGGER : CR3000 datalogger installed. Wiring standardized. |
19-NOV-08 |